Current Construction Activities
Listed here are the current ongoing construction activities on the bridges and on the roadway section of I-476
Summer 2010
On the Schuylkill River Bridges
- Northbound bridge completed.
- Construction completed on outside two lanes of southbound bridge.
- Build new deck on inside two lanes of southbound bridge.
On the I-476 Roadway between I-76 and Turnpike Interchange
- Complete reconstruction of outside half of southbound interstate.
- Complete resurfacing of outside half of southbound bridge decks.
- Continue sinkhole remediation in southbound shoulder, median
- Reconstruct shoulders on Ridge Pike at approach to I-476 overpass.
- Reconstruct ramps.